Deliverables & Milestones

The target work plan is:We are using an iterative approach to design of the GF treating governance as product and code.  The overview of this process is here.

#

Name

Description

Delivery Date

Status

Link

1

Defined purpose & Principles

Based on Requirements definition and stakeholder feedback - based on Principles of SSI and core business, legal, ethical and technical requirements of Yoma

30/04/2021

2

Special requirements definition

AI/ML, MRG and token requirements defined including additional or associated controlled documents, policies and principles

31/05/2021

3

Outline document package

Based on ToIP metamodel defines all components of the GF that need to be drafted

30/06/2021

4

Draft Master Document

The main Governance Framework document in a draft format to begin review cycles

30/07/2021

5

Draft Controlled Docs & Contracts

As identified in 4. Outline Document Package to begin review cycle

31/08/2021

6

Governance Framework V1

Finalised Governance Framework V1 

30/09/2021

7

Recommended next steps for implementation

Identifies any issues, future scope questions, and recommended GF iteration approaches.Sprint 0

Define core principles, purpose, objectives and scope, agree approach

31/05/2021

CompletePrincipal Document Ecosystem GF 

2

Sprint 1

Test the Agile Approach:  Youth Journey, DESIGN, DEV

15/06/2021

In process

3

Sprint 2

Provider Journeys DESIGN, DEV, TEST

31/07/2021



4

Sprint 3

Mop Up & TEST, Prepare to deploy

30/08/2021



5

Sprint 4

Deploy

30/09/2021



Chairs/Convenors

...